What does an ADU cost in Montgomery County?
Straight answer: most projects land between roughly $80,000 for a simple basement conversion and $400,000+ for a custom detached build. But square footage isn't what decides the number — site conditions, utilities, sprinklers, and approvals are. Here's how to build a realistic budget before you talk to anyone.
They're illustrative figures compiled from public Maryland and Montgomery County reporting as of July 2026, not quotes for your property. A quote depends on your lot, your utilities, your finishes, and current market pricing. Treat these as a way to sanity-check a budget, not to set one.
Why square footage is the wrong starting point
A 700-square-foot detached ADU on a flat lot with public water and sewer at the street is a fundamentally different project from the same 700 square feet on a sloped Potomac lot with a septic system and mature trees. Same size, very different cost. That's why a per-square-foot number is only a rough sanity check — the site conditions and approvals are what actually move a Montgomery County ADU budget.
The budget lines that decide the number
A realistic ADU budget is a stack, not a single figure. Here's what sits on top of the base structure cost:
- Design & feasibility. Architectural drawings, and often a feasibility study before you commit — cheap insurance against buying plans that won't fit your lot.
- Survey & engineering. A current survey, plus structural and sometimes civil engineering, especially for detached builds and grading.
- County & municipal approvals. DHCA Class 3 ADU licensing and DPS permits — and separate review if you're in Rockville, Gaithersburg, or Takoma Park, or in a historic district.
- Site preparation. Clearing, grading, tree protection, retaining walls, and drainage. This is where sloped or wooded lots get expensive fast.
- Utility connections. Water, sewer or septic, electric, and gas. Septic properties (common in Potomac) can face significant added cost or feasibility limits.
- Fire sprinklers. Detached ADUs generally require a residential fire-sprinkler system — plan on roughly $5,000–$15,000+ depending on size and water supply. Homeowners routinely miss this.
- Structure & finishes. The build itself, where your finish level swings the per-square-foot number the most.
- Landscaping & restoration. Putting the yard back together after construction.
- Financing costs. Interest and fees if you're borrowing against equity or using a renovation loan.
- Contingency. A sensible 10–15% buffer for the surprises that older properties reliably produce.
The three big cost drivers in Montgomery County specifically
Sprinklers on detached units. Because detached ADUs generally require sprinklers, a detached build carries a cost floor that a basement conversion doesn't. If budget is tight, an attached or basement ADU is usually the more economical path.
Septic vs. public sewer. Large-lot areas like Potomac often run on septic. Adding a dwelling unit to a septic property can trigger system upgrades or capacity questions that reshape both cost and feasibility — worth checking early.
Setbacks shrinking the buildable size. Detached ADUs face greater setbacks, and on smaller R-60 lots the buildable footprint can shrink to around 576 square feet. A smaller unit isn't always cheaper per foot — fixed costs like design, permits, utilities, and sprinklers don't shrink with it.
Cost figures are editorial planning ranges compiled from public reporting, not contractor quotes or an appraisal. Regulatory requirements that affect cost (sprinklers, setbacks, licensing) may change — Maryland's HB 1466 requires every county to allow ADUs on single-family lots by October 1, 2026. Confirm current requirements with Montgomery County DHCA and DPS and get a real quote from a licensed builder before budgeting a project.
A planning range is a start. Your property decides the rest.
Start a project review and we'll screen feasibility and match you with a licensed Montgomery County builder who can quote your actual site.
Related guides
Detached ADU builders
What's different about a detached backyard build — and why it carries a cost floor.
Read →Permits & rules
The DHCA + DPS path, licensing, sprinklers, and municipal differences.
Read →Bethesda ADU builders
How high-value, compact lots change the ADU math in Bethesda and Chevy Chase.
Read →